Burbank Permit Guide

A complete, step-by-step playbook for navigating the City of Burbank permitting process — from zoning validation to Certificate of Occupancy.
Building Permits Portal EconDev Concierge

1. What Triggers a Permit

California Building Code & Burbank Municipal Code

You NEED a permit for: New buildings or structures, additions (rooms, second floors, ADUs), interior remodels (walls, layout changes), electrical upgrades (panels, rewiring), plumbing (re-piping, sewer, fixture changes beyond simple swaps), HVAC installs or replacements, roof replacements (depending on scope), commercial signage, and demolition (partial or full).

You typically DON'T need a permit for: Cosmetic work (paint, flooring, cabinets) and minor repairs (replacing a faucet or outlet).

When in doubt, confirm. Burbank is strict about enforcement. Building Permits reference →

2. Permit Types

Over-the-counter, plan check, and specialized
Over-the-Counter (Quick)
Water heater, electrical panel swap, minor plumbing. Same day to a few days.
Plan Check Required
Residential remodels, commercial tenant improvements, new construction. Full multi-department review.
Specialized Permits
Grading, demolition, temporary use, sign permits — each with unique requirements.
View all permit applications →

Every Burbank permit, linked

Straight to the right city page — no hunting through burbankca.gov
Alarm Permit
Police · $100 · burglar/security alarms
Building Permit
Electrical, mechanical, plumbing, remodels, ADUs
Business License / Tax
Register or renew a Burbank business
Film Permit
Film Burbank · productions, drones, street closures
Fire Alarm Permit
Fire Department · Fire Prevention
Fire Sprinkler Permit
Fire Department · plan check
Hazardous Materials Permit
Fire Department · hazmat program
Underground Storage Tank
Fire Department
Special Effects / Pyro Permit
Fire Department · film safety
Garage Sale Permit
Apply online
Encroachment / Excavation
Public Works · incl. outside dining
Street Use Permit
Rolloff bins, moving trucks, cranes, no-parking signs
Oversized Load Permit
Public Works · transportation
Open House Sign Permit
Public Works · annual, July–June
Water Discharge Permit
Draining a pool to the street
Sewer Connection Permit
Public Works · sewer fees
Parking Permit
Community Development · incl. RV/boat/trailer
Park Reservations & Permits
Parks & Recreation
Swimming Pool Permit
Build a pool or spa · Building & Safety
Solar System Permit
Burbank Water & Power instructions
Special Event Permit
Economic Development

3. Pre-Application & Entitlement Phase

The most critical step — where experienced developers win or lose time

Before submitting plans, verify zoning compliance: setbacks, height limits, parking requirements, and use restrictions. You may also need a Conditional Use Permit (CUP), variance, or design review — if so, you're in the planning approval stage, not permitting yet.

Departments involved: Planning Division, Public Works, Fire Department, and Burbank Water & Power.

Zoning & land use info → · EconDev concierge →

Strategic tip: Use the Economic Development concierge early. They help coordinate departments and reduce friction — this alone can save weeks.

4. Application Submission

What you submit and how it works

What you submit: Permit application form, full plan set (PDF format), structural calculations (if applicable), energy compliance (Title 24), and supporting documents.

How to submit: Email or online. Larger projects use ProjectDox, the city's digital plan review system.

Plan submittal info →

5. Plan Check Process

The core bottleneck — understanding review cycles

Departments reviewing: Building & Safety, Planning, Fire, Public Works, and Utilities. They check code compliance (California Building Code), fire access and safety, structural integrity, ADA compliance, and utility connections.

Timeline reality: First review takes approximately 6–8 weeks. Each correction cycle adds 2–4 weeks. Typical projects go through 2–4 rounds of corrections. Real-world total: 2–4 months minimum for most projects.

What slows this down: Incomplete drawings, poor coordination between architect and engineer, ignoring zoning early, and weak resubmittals.

Strategic tip: Treat resubmittals like proposals — clean, complete, and coordinated. This is the single biggest factor in avoiding delays.

6. Fees

Layered fees that can escalate quickly

Core fees: Plan check fee, permit issuance fee, and inspection fee.

Additional fees: Development impact fees, utility connection fees, and school district fees (in some cases).

Example ranges: Small permit: $200–$1,000 · Remodel: $2,000–$15,000 · Large development: $50K–$500K+ total fees. Fees are not just administrative — they fund infrastructure impacts.

Fee schedule → · Municipal code →

7. Permit Issuance

What happens after approval

You receive your permit after all departments approve, all corrections are resolved, and fees are fully paid.

Important: Permits expire if work doesn't start within 180 days. Extensions are possible but not guaranteed. You must keep inspections active to keep your permit alive.

8. Construction & Inspections

Inspection stages you must follow

Typical inspection stages: Foundation, framing, electrical, plumbing, HVAC, and final inspection. Work must follow these stages — you cannot proceed freely.

Scheduling: Online or by phone, usually with next-day availability.

Key rule: Failing an inspection means stop work until corrections are made and the inspection is passed.

Schedule an inspection →

9. Certificate of Occupancy

Final step before legal use

All inspections passed, no outstanding corrections, and all fees cleared = you receive a Certificate of Occupancy (CO).

Without a CO, you cannot legally occupy or operate. This applies to both residential and commercial projects.

10. Realistic Timelines

What to actually expect
Project Type
Timeline
Minor permit
Same day – 1 week
Small remodel
1–2 months
Tenant improvement
2–4 months
Ground-up build
6–12+ months

Biggest delays: Planning approvals, plan check correction cycles, and contractor scheduling.

11. Common Pitfalls

Mistakes that cost time and money

Skipping zoning validation — leads to full redesign mid-process.

Submitting incomplete plans — adds months to the timeline.

Underestimating fees — kills project budgets unexpectedly.

Poor consultant coordination — creates conflicting corrections between architect and engineer.

12. Strategic Playbook

How to move faster through the process
1Run zoning + feasibility first — before any design work begins.
2Engage the city early — use the EconDev concierge or a city planner.
3Submit a clean, coordinated plan set — incomplete plans are the #1 delay.
4Respond to corrections fast and thoroughly — treat resubmittals like proposals.
5Schedule inspections proactively — don't let gaps stall momentum.

Quick Links

All permit resources in one place
Building Permits Portal
Main page for all building permit info
Permit Applications
Download application forms
Plan Check Review
Plan submittal and review process
Schedule Inspection
Online inspection scheduling
Forms & Fee Schedule
All forms, applications, and fee info
EconDev Concierge
Free help navigating zoning & permits
Contact Community Development
Address: 150 N Third St, Burbank, CA 91502 · Phone: (818) 238-5250 · Website: burbankca.gov/community-development